Kerr Engineering was engaged by provider of engineering services to the Oil and Gas industry to manufacture 12 Mud Mats to support well-head work.
Scope of work:
- Manufacture of the mud mats in accordance with DNV 2-7.1 specifications
- Complete all welding to AWS D 1.1 Structural Welding Code
- Complete the coating application to the design specification
- Co-ordinate independent NDT and load testing
- Supply comprehensive MDR’s outlining material specification and testing, weld procedures and welder qualifications, and a coating application report
Outcome:
- Despite an extremely compressed timeframe, the Mud Mats were produced to spec and delivered on time.